WBUT Question Paper For BSCM 3rd year Student PROJECT MANAGEMENT & SUPPLY CHAIN PROCESS REDESIGN (CS/BSCM/SEM-6/BSCM-602/2012) Question paper

Submitted by Anonymous (not verified) on Thu, 08/28/2014 - 22:00

CS/BSCM/SEM-6/BSCM-602/2012

2012

PROJECT MANAGEMENT & SUPPLY CHAIN

PROCESS REDESIGN

Time Allotted : 3 Hours                                                  Full Marks : 70

The figures in the margin indicate full marks.

Candidates are required to give their answers in their own words

as far as practicable.

GROUP – A

( Multiple Choice Type Questions )

1. Choose the correct alternatives for the following : 10 × 1 = 10

i) Social cost benefit is also termed as

a) project cost b) economic analysis

c) cost flow d) none of these.

ii) Technical risk is a/an

a) external risk b) internal risk

c) systematic risk d) all of these.

iii) Which of the following is not a measure of risk ?

a) Range b) MAD

c) Variance d) Correlation.

iv) Pass off matrix is a tool of

a) Cost analysis b) Risk analysis

c) Sensitivity analysis d) none of these.

v) Cost control may be of

a) two types b) three types

c) four types d) five types.

vi) In Damin cycle for project management, check stage is the

a) second stage b) first stage

c) fourth stage d) third stage.