CS/BSCM/SEM-6/BSCM-603/2011
2011
INTERNET TECHNOLOGY &
SUPPLY CHAIN MANAGEMENT
Time Allotted : 3 Hours Full Marks : 70
The figures in the margin indicate full marks.
Candidates are required to give their answers in their own words
as far as practicable.
GROUP – A
( Multiple Choice Type Questions )
1. Choose the correct alternatives for the following : 10 × 1 = 10
i) CRM stands for
a) Common Supply Man
b) Customer Relationship Member
c) Customer Relationship Management
d) Consumer Relationship Management.
ii) The greatest risk in IT is
a) verification b) initiation
c) modernization d) installation.
iii) In TMF, F stands for
a) formation b) foundation
c) function d) facilitation.
iv) Which of the following costs does not affect by
e-business ?
a) fund transfer b) transportation
c) inventory d) facility.
v) A production schedule DSS can use
a) simulation technique