WBUT 2011 BBA (SEM-4) PRODUCTION MANAGEMENT QUESTION PAPER

Submitted by Anonymous (not verified) on Thu, 08/28/2014 - 12:41

CS/BBA (H), BIRM, BSCM/SEM-4/BBA-401/2011

2011

PRODUCTION MANAGEMENT

Time Allotted : 3 Hours                    Full Marks : 70

The figures in the margin indicate full marks.

Candidates are required to give their answers in their own words

as far as practicable.

GROUP – A

( Multiple Choice Type Questions )

1. Choose the correct alternatives for the following : 10 × 1 = 10

i) Plant location decisions concerned both

a) Manufacturing & Assembly

b) Design & Variety

c) Design & Quality

d) Design & Value.

ii) Process layout requires comparatively more space than

..................... layout.

a) Piece b) Design

c) Product d) Special.

iii) Hand trucks and trolleys are examples of

a) materials handling equipment

b) flow diagram

c) machine capacity chart

d) scheduling.

iv) In method study, “→” symbol represents,

a) Inspection b) Operation

c) Transportation d) Delay.

v) Normal time is also called

a) Basic time b) Standard time

c) Observed time d) none of these.

vi) Production is defined as the

a) manufacturing of goods

b) manufacturing of services

Attchments

Comments

Related Items